Interior Construction Progress Update!

A lot has been going on inside the Glen Park Rec Center! During the first few weeks of November the construction team has been busy installing new windows, insulation, and mechanical systems. The structural framing for the climbing wall is also complete while the restrooms are being prepared for the arrival of new fixtures. The following photos offer a glimpse of the work currently underway.

Img 0215

New insulation, new windows, and seismic structural upgrades in the renovated gymnasium.

Img 0214

The new “front door” to the Rec Center allows for natural light and improved visibility.

Img 0212

Framing for the new welcome desk in the lobby.

Img 0218

Restored beams over the auditorium looking toward the climbing wall space.

Img 0219

Structural framing for the climbing wall.

Img 0222

New operable windows in the auditorium will allow for natural ventilation.

Img 0225

New windows being installed in one of the multi-purpose rooms.

Img 0226

Roughed-in plumbing in one of the restrooms prior to the installation of new sinks.