Getting ready for the August 3, 2013 Grand Opening

Cabrillo children's area

The Site work is substantially complete and the Clubhouse is about to be completed in a couple of weeks.    All the renovation work is looking great and the landscape is giving a wonderful framework.   The donor tiles started to be installed at the seatwalls this week and will be completed on the week of July 8.   The concrete ping pong table donated by the Friends of Cabrillo Playground will arrive on site next week.  The  contractor is doing punchlist work for the site and clubhouse in the month of July.