Helen Diller Playground Construction Update. 12/05/11

Progress that was made this week includes:

  • The Contractor continues to make good strides this week on the concrete flat work. Crews formed and poured the bridge abutments, walls at the sand table, finished pads for the climbing wall, net anchors and slabs this week.
  • Work on the irrigation lateral lines and sprinkler head installation is ongoing.  Grading along the ADA path and gravel placement, excavation of electrical trenches and placement of conduit is also continuing.