Balboa Pool Construction Update!

The project is approximately 22% complete. In terms of progress, the months of January and February has been a very wet one, thus slowing down considerable the progress of work in the past few weeks. This has impacted the contractor’s ability to perform some of its planned activities.

Fortunately this week, with  dry weather, the contractor is taking advantage and  proceeding on the following  activities;

  • Demolition and abatement activities on the interior is substantially complete;
  • Layout for the seismic foundation work have commenced in earnest;
  • Layout for utilities including the main drains for the pool are ongoing; and
  • Contractor has also commenced on formwork for the curbs also.

We will continue to provide additional update on progress. Thanks for your patience and continued support for the project. Thanks