Lake Merced Improvement Project Community Meeting #2 on 1/12/17

We had great turn-out for the second Lake Merced Improvement Project community meeting on 1/12/17. Thank you to everyone for your constructive feedback and support for the project. Among the potential scope elements we discussed were improvements to the perimeter path and fitness equipment, environmental and erosion control issues, and … Continue reading

Mountain Lake Park Playground Construction Update 1/23/2017

The Mountain Lake Playground Renovation is now approximately 85% complete. The final concrete walls at the summit area were poured earlier this week, leaving just the sidewalk up to the slide and the concrete overlook platform as our remaining concrete work. We have also started installation of the decking surface … Continue reading

Hilltop Opening 12/3/2016

After almost a year of construction, Hilltop (Sundial) Park is completed! The park showcases new accessible paths that lead to the new playground, new skateboard park, restored great lawn, and to infamous sundial. Please join us to celebrate on Saturday, 12/3/2016 at 10AM-1PM, for music, food and fun!  

Mountain Lake Park Playground Construction Update 12/1/2016

We continue to make good progress on the Mountain Lake Playground Renovation, which is now approximately 75% complete. Completed work includes sloped concrete slabs in play areas, approximately half of the concrete flat work, stairs, installation of the steel “trees” at the overlook, the majority of low landscaped walls, irrigation … Continue reading

Washington Square Playground meeting on 11/9/2016

Thank you to all the community members who attended the last Washington Square Playground meeting on 11/9/2016. Feedback for the proposed concept design was overwhelmingly positive, and we received many thoughtful comments on the treatment of the play surface, the overall materials/color palette, seating, and the play structures. Please see … Continue reading

Lake Merced Improvement Project Meeting-11/3/2016

Thank you to the approximately 20 community members who attended the first Lake Merced Improvement Project meeting on 11/3/2016. We received lots of good/productive feedback on a variety of programs at the lake, including trail improvements, boating, pedestrian/bike safety, water recreation, and more. Lake Merced is clearly well loved! As … Continue reading

John McLaren Bike Park out to Bid

Rec Park is thrilled to announce that the John McLaren Bike Park Project is out to bid! Information on the bid solicitation can be found here: http://mission.sfgov.org/OCABidPublication/BidDetail.aspx?K=11233 Key Information: Pre-Bid Conference Date – September 7 at 11:00am Bids Due – September 22 at 2:30 pm at McLaren Lodge, 501 Stanyan … Continue reading

Washington Square Playground Community Meeting #2

Thank you to those who attended community meeting #2 on June 22nd for the Washington Square Playground Renovation. The project is a work in progress, and your participation has been invaluable. We know there are many community members who would like to attend these meetings but are unable. In an … Continue reading

Construction starting soon

The contractor (Alta Engineering) is scheduled to begin the site surveys this month. Step demolition and construction of the new steps will follow the survey task. Currently the contractor is projecting that trail construction work will occur June through August. During construction, access to the top of Tank Hill will … Continue reading

Updated Schedule for Construction

We are pleased to inform that the Recreation and Park Commission awarded a construction contract for the 17th & Folsom Street Park project at their Meeting of December 17, 2015.   The construction contract is currently under certification and start of construction is anticipated in March 2016. The anticipated construction schedule … Continue reading

Buchanan Mall Activation Opening Celebration 11/7/2015

Change is coming to the Buchanan Street Mall.  The Design Task Force – a group of 30 neighborhood elders, youth, and adults – met weekly this summer to discuss design and stewardship of the Mall. The Exploratorium translated the community’s design ideas into Activation elements.  These elements – gardens boxes, … Continue reading

Urban Ag Academy

Grow it, Preserve it, Love it! SF County Fair Building, 9th and Irving, Saturday, September 12, 2015, 11:30a-5pm Join the Urban Agriculture Program and partners for Urban Ag Academy: Grow It, Preserve It, Love It! This one-day event will feature demonstration classes on gardening and garden-infrastructure, workshops on fermenting and … Continue reading

Beach Chalet Update

The Beach Chalet Athletic Field project is moving forward as planned.   The contractor has completed their rough grading operation and is now moving forward with the storm drainage pipe installation.   This work will continue over the next month.   Other work items that have been completed include the removal of hazardous … Continue reading

West Sunset Playground Update

We are happy to report that the construction documents have now been submitted to the Department of Building Inspection for review and approval.   Our schedule currently shows that we will have completed bid document at the beginning of March.    Once these drawings have been approved we will be sending them … Continue reading

Great Highway Restroom Update

The restroom project is proceeded as planned.   To date, new electrical, plumbing and mechanical equipment has been installed.   Interior finish work will continue over the next two months along with exterior improvements such as painting and landscape.  Recent site improvements include new roofing,  new entry ramp/handrails, new sidewalks and curb … Continue reading

THIRD COMMUNITY MEETING FOR MCLAREN COMMUNITY GARDEN IMPROVEMENTS

Hi all, Thank you so much to those who came to the third community meeting to discuss the design of the McLaren Community Garden. We received lot of positive feedback on the overall concept design plan. We also got valuable input such as incorporating ramps for wheelbarrows, and requests to … Continue reading

Failing Playgrounds Meeting #7 Summary

At the final meeting of the Failing Playgrounds Task Force on November 18, 2014, members and the public reviewed the draft Failing Playgrounds Final Report, detailing the process of the Task Force, methodologies, and recommendations of playgrounds for renovation. The report highlighted the Task Force’s conclusion that removing CCA-treated wood from … Continue reading

Second Meeting for McLaren Community Garden Improvements

Hi everyone! We had a productive second meeting discussing two different design options for the renovation of the McLaren Community Garden. We got great feedback on elements such as trees that should be preserved, utilizing tall perimeter fencing and designing raised beds with attached seating. There was a lot of … Continue reading

Calling Alemany Farm CAC members and Interested Stakeholders!

The Recreation and Park Department seeks a replacement for the Alemany Farm CAC (Community Advisory Committee)’s Seat 2, Neighborhood Resident.  While not required, preference should be given to San Francisco Housing Authority residents.  The CAC is responsible for guiding and overseeing site programming, and recommended programming to the Recreation and … Continue reading

SF Conservation Corps to begin preparation work for new trail Aug. 8

We are excited to report that we are beginning Phase I of the Twin Peaks Trails Improvement Project.  Phase I is part of our “Creeks to Peaks” initiative to connect Glen Canyon with Twin Peaks.  Beginning on August 8, the San Francisco Conservation Corps will be clearing blackberry, ivy and … Continue reading