News Flash

Posted on: February 10, 2020

GEORGE CHRISTOPHER: PROGRESS DURING THE WET WINTER MONTHS

Capital Project Update

Construction is moving along at George Christopher Playground!

The playground demo progressed quickly in the fall, and the site has been a little more quiet this winter due to rain. Until this past Friday, the soil was too wet to pour concrete due to Janua...

Read on...

George Christopher Playground Improvement Project
Posted on: October 28, 2019

CONSTRUCTION BEGINNING SOON AT GEORGE CHRISTOPHER PLAYGROUND

Capital Project Update

After many years of community process and design, construction on the George Christopher Playground renovation will begin in early November 2019!

Starting next week, the construction team will begin installing fencing to protect trees and temporary fencing...

Read on...

George Christopher Playground Improvement Project
Posted on: May 16, 2018

GEORGE CHRISTOPHER PLAYGROUND PROJECT IS GOING OUT TO BID SOON!

Capital Project Update

George Christopher Playground renovation includes: site work/playground renovation, paving, restroom upgrades, maintenance road work and irrigation work. We plan to go out to bid in mid July 2018 and are aiming for a construction start date December 2018....

Read on...

George Christopher Playground Improvement Project
Posted on: May 12, 2017

GEORGE CHRISTOPHER FINAL CONCEPT RENDERINGS

Capital Project Update

Hi Everyone!

As an update to my last post, we have updated our renderings for the George Christopher project and I wanted to share them with you today. See the link below:

George Christopher Final Concept

We will be presenting this concept to the Recreation&...

Read on...

George Christopher Playground Improvement Project