Youngblood Coleman Synthetic Turf Replacement

Youngblood Coleman FieldDescription

Synthetic turf was installed at the Youngblood Coleman soccer field over ten years ago. This field is at the end of its useful life and is in need of replacement.

Scope of Work

Replace turf, turf infill, and turf underlayment pads; drainage improvements; lighting improvements; improvements and repairs to the existing perimeter fence and gate systems; replace select site furnishings.

Funding Source

Funding comes from the Recreation and Parks Department General Fund and Playfields Fund.

Thank You

Thank you for your patience while we complete these improvements.

  1. Capital Project Update

    Construction Update JAN 2020

    Contractors have begun removing the old synthetic turf and infill at the soccer field Read on...
  2. Capital Project Update

    Construction Award Update

    The construction contract for this project has been awarded to Robert A. Bothman Construction Corporation and Yerba Buena Engineering Read on...
  3. Capital Project Update

    Preparing to Bid

    We are in the home stretch of preparing the bid package and plan to put this project out to bid Read on...
  4. Capital Project Update

    Design Underway OCT 2018

    Verde Design, Inc. is moving along with the design of this project Read on...
  1. Monica Scott

    Project Manager
    Phone: 415-581-2546